Tariff-RWC BADNERA, MAHARASHTRA

TARIFFS APPLICABLE AT BADNERA, MAHARASHTRA
Storage wef 01-05-22
Handling wef 16-02-22

 

ITEM RATES SCHEDULE FOR FERTILIZER /CEMENT/SALT : Appendix-IV-A

Sr.No. Description of Services Rates per MT (in Rs.) Fertilizer/Salt/Cement At RWC Siding
Jute/HDPE Bag Paper Bag
1(a) For unloading bags of Fertilizers/Cement/Salt from wagons/ rakes/ jumbo rakes / trucks or any other transport vehicle and stacking the bags on the platform/ground if required and then stacking the same in the godowns wherever necessary upto the prescribed height as mentioned in Section-VI-(B)-1(i) (a). 104/- 160/-
1(b) For taking out the bags of Fertilizers/Cement/Salt from the stack and loading them into the parties’ truck/ wagon for delivery/dispatch as mention in Section-VI-B- 1(i) (b). 104/- 160/-
2(a) For unloading bags of Fertilizers/Cement/Salt from wagons/trucks or any other transport vehicles and directly loading them into the trucks/wagons as per Section-VI-B- 1(ii) (a). 207/- 118/-
2(b) For unloading the bags of Fertilizers/Cement/Salt from wagons/trucks or any other transport vehicles and directly loading them into the trucks/wagons across the warehouse as mentioned in Section-VI-B- 1(ii) (b) 207/- 118/-
3 Shifting of such quantity of Fertilizers/Cement/Salt as may be required day to day by the Terminal Manager from one godown to another godown or from one compartment to another compartment in the same premises as per Section-VI-B-2. 136/- 315/-
4 For unloading the bags from wagons and stacking at the platform/ ground loading into trucks, transferring to other shed (s), unloading & stacking inside the godown as mentioned in Section-VI-B-(4) 136/- 315/-
5 For supply of Casual Labour as mentioned in Section-VI-B-(3). MW MW

 

ITEM RATES SCHEDULE FOR FOODGRAIN /ANY OTHER NOTIFIED COMMODITIES: Appendix-IV-B

Sr.No. Description of Services User Tariff
in Rs. per MT
1(a) For unloading bags of foodgrain and any other notified commodities from wagons/ rakes/ jumbo rakes / trucks or any other transport vehicle and stacking the bags on the platform/ground if required and then stacking the same in the godowns wherever necessary upto the prescribed height as mentioned in Section-VI-B-1(i) (a). 124/-
1(b) For taking out the bags of foodgrain and any other notified commodities from the stack and loading them into the parties truck/ wagon for delivery/dispatch as mention in Section-VIB-1(i) (b) 124/-
2 For unloading bags of foodgrain and any other notified commodities from wagons/trucks or any other transport vehicles and directly loading them into the trucks/wagons across the warehouse as per Section-VI-B--1(ii) (a). 248/-
3 Shifting of such quantity of Foodgrain and any other notified commodities as may be required day to day by the Terminal Manager from one godown to another godown or from one compartment to another compartment in the same premises as per Section-VI-B-(3). 192/-
4 For unloading the bags from wagons and stacking at the platform/ ground loading into trucks, transferring to other shed (s), unloading & stacking inside the godown as mentioned in Section-VI-B-(5). 192/-
5 For supply of Casual Labour as mentioned in Section-VI-B-(4). Minimum wages as fixed by appropriate authority in the State

ITEM OF SCHEDULE FOR HANDLING OF STOCK AT NON RWC SIDING SIDE OF RWC SIDING WITHIN SAME VICINITY: APPENDIX- IV-C

Sr.No. Description of Services (User tariff) Rates per MT (in Rs.)HDP Paper bag
1(a) For unloading the bags from wagons /rakes/ jumbo rakes/trucks or any other transport vehicle and stacking the bags on the platform /ground upto the prescribed height as mentioned in Section-VI-B- 1(iii) (a). 115/- 173/-
1(b) For taking out the bags from the stacks in the platform/ ground and loading them into the parties truck/ wagon for delivery/ dispatch as mentioned in Section-VI-B-1(iii) (b). 115/- 173/-
2 For unloading the bags from wagons/ trucks or any other transport vehicles and directly loading them into the parties trucks/ wagons for delivery/ dispatch as mentioned in Section-VI -B-1 (iii) (c). 226/- 340/-
3(a) For unloading the bags from wagons and stacking at the platform/ ground loading into trucks, transferring to RWC, unloading & stacking inside RWC godown as mentioned in Section-VI-B-1( iii) (d). 340/- 430/-
3(b) For taking out the bags from stacks in the RWC godown and load them into the truck and carry it to non-RWC siding, stacking in the platform/ ground if required and loading into the wagon as mentioned in Section-VI-B-1 (iii)(e) 340/- 430/-
General Tariff (For Storage) Days (Rs. per MT per Day)
  1 st day 17
2-3 day 22
4-6 day 28
7-15 day 33
16- day onwards 50

(w.e.f. 21.04.2022)

Management charges Rs. 20/- per MT
Storage reservation charges Rs. 155/- per MT per Month

Insurance & Documentation Charges W.e.f 01.05.2022

S.No. Description Rate Per MT
1 Cement Rs.8
2 Sugar Rs.9.50
3 Fertilizer/foodgrain/salt/soda Rs.7
4 Pulses Rs. 17/MT/Month

 

Storage Tariff for Reservation(per sq. meter)for Parcel/Cold chain/e-Commerce business(w.e.f-01.05.2022)

S.No. Description Per sq. meter per Month
1 Reservation Charges for Parcel/Cold chain/e-Commerce business Rs.222

*Reservation charges for cement is Rs.154/- (per MT/month) wef 01.05.22.

*Reservation charges for Fertilizer is Rs.100/- (per MT/month) wef 01.05.21.

*Goods and services taxes as aplicable shall be levied extra on the above rates from user as applicable from time to time.

For handling of open wagons 25% extra payment will be charged from user as per our existing provision.

1. Tariff of other commodities not lined above, please contact the undersigned.

2. The tariff is subject to change at the discretion of CRWC and the correct tariff may be confirmed with the respective RWC Terminal Manager.

3. Necessary Service Tax as prevalent will be applicable in addition.

4. For any long-term committed volumes in mutual business interests, please contact:


Fax No.: 011-23379434